New Jersey Environmental Infrastructure Trust
The State of NJ's Infrastructure
Program InformationFormsPublicationsFAQsRelated LinksAbout UsContact UsHome
New Jersey Environmental Infrastructure TrustNew Jersey Environmental Infrastructure Trust
HOW THE LOAN PROGRAM WORKS
  The loan process follows a 13-month cycle that begins in October and ends the following November. Use the information and schedule below to gain a better understanding of how to apply for a loan. As attested by many of our borrowers, it’s not more complicated than traditional financing.
  Program Rules (NJDEP Website)
N.J.A.C. 7:22
Financial Assistance Programs for Environmental Infrastructure Facilities (PDF Format)
Loan Structure
  Borrowers receive loans in two equal parts: Approximately one half to three quarters comes from a zero interest State Revolving Fund (SRF) maintained by the DEP. The other portion comes from proceeds of highly rated tax-exempt revenue bonds sold by the Trust. Combining these two funds results in a loan that is 50 to 75% lower than traditional loan rates.
   
Pre-Award Program
 

This process addresses conflicts between a borrower's construction or land acquisition schedule and the finance program's 13 month cycle. When borrowers must commence construction or close on a land acquisition prior to the November loan closing, a pre-award approval can be issued. This approval allows borrowers to either seek interim financing themselves or apply to the Trust for interim financing. Pre-Award Approval must be received both from the NJDEP and the NJEIT prior to commencement of work. Upon receipt of Pre-Award Approval, a borrower may immediately advertise for bids. Work performed pursuant to contracts that were bid or awarded prior to Pre-Award Approval is ineligible for NJEIFP funding reimbursement.

Pre-Award Approval Eligibility (Non-Emergency Conditions, see N.J.A.C. 3:11-3.11)

Borrower Submission Requirements Deadline
Fall Loan Submission Package
Planning Documents
Loan Application
Identification of all required NJDEP permit applications and evidence of application submission
Design Documents
Contract Documents containing SED provisions (N.J.A.C. 7:22-9.12(a))
SED Utilization Plan

Program Approval
Borrower compliance with Borrower Submission Requirements
Design Document Approval
Planning Document Approval
Confirmation that Borrower has received all relevant permits
SED Approval
NJDEP issues Pre-Award Approval
Borrower passes Reimbursement Resolution
Determination of the availability of funds
NJEIT issues Pre-Award Approval
Borrower advertises for bids
SED Utilization Plan
   
Interim Project Financing
 

Ready to go before November? Interim Project Financing (IPF) allows borrowers to access capital prior to the regular November loan closing. It is available to borrowers that have submitted a Loan Request and have been 1) granted all required DEP approvals, 2) have been granted pre-award approval by the DEP and the Trust and 3) are ready to start their project. Loans are available in January each year up to a maximum of $10 million dollars per project. All interim loans are converted into permanent financing in November. Click here to access the Interim Project Financing program applications.

IPF Loan Eligibility (Requirements for IPF Loans issued after May1)

Receive Pre-Award Approval No Later Than (NLT) 30 days prior to loan closing
Submit a Financial Addendum Form (FAF) March 23
Submit an IFP Financial Addendum Form March 23
Be identified in a NJEIFP January or May Legislative Report Prior to loan closing
Pass Local Bond Ordinance NLT 30 days prior to loan closing
Receive LFB/BPU Approval NLT 30 days prior to loan closing
Comply with all other FAF requirements NLT 30 days prior to loan closing
IFP Closing  
Borrower submits requisition forms NLT 30 days prior to disbursement
   
LOAN PROCESS
October 15 – Loan Request and Planning Document Deadline
  Plan to meet with DEP personnel well in advance of this date to clarify all aspects of the program. Borrowers are required to submit a Loan Request Form and planning document to DEP and the Trust by October 15. A Loan Request informs the NJEIT of your interest to pursue financing for a project in the upcoming financing cycle. Loan Request forms received after October 15 will be considered for the following financing cycle.
Forms
   
January
Interim financing is available for projects with pre-award approval.
   
February
The Trust conducts seminars with borrowers to outline the entire loan process and answer any questions. Click Here for the current seminar schedule.
 
March
Submit your loan application and design documents to DEP.
Start applying for required permits. If you have question about what permits will be necessary please contact Stanley Cach, Assistant Director, Municipal Finance and Construction Element at (609) 292-8961. Click here to view average permit review times from DEP Permit Activity Reports.
Secure a Bond Counsel and a Financial Advisor.
   
Financial Addendum forms are due in April. These forms are checklists of items needed by the Trust. CLICK HERE to access these forms.
 
April
Borrowers must apply for Local Finance Board (LFB) approval.
Local Finance Board Application
Applications are considered at the board’s meetings (LFB Meeting Schedule). Borrowers should choose their desired meeting date and submit their application by the due date specified for that meeting.
Borrowers under Board of Public Utilities (BPU) jurisdiction must submit a request for approval to incur debt.
Borrowers return completed Financial Addendum Forms (FAF) to Environmental Infrastructure Trust.
   
May
  Late submission of LFB or BPU applications.
   
June
The Trust board adopts a resolution authorizing loans and agreements.
The Trust’s Bond Counsel distributes Draft #1 of the Loan, Escrow and Continuing Disclosure Agreements to borrowers.
The Trust’s Bond Counsel distributes Draft #1 of Trust Bond Resolution to borrowers.
Both houses of the legislature must approve the projects.
   
July
Borrowers submit written comments to Draft #1 of Loan, Escrow and Continuing Disclosure Agreements to the Trust, the Trust’s Bond Counsel and Trust’s General Counsel.
The Trust’s Bond Counsel addresses borrower’s written comments and distributes Draft #2 of the Loan, Escrow and Continuing Disclosure Agreements to borrowers.
   
August
Borrowers and counsels complete or submit any missing documentation and obtain all necessary permits.
The DEP issues a Project Certification. To receive Project Certification, all planning, design, environmental requirements and permits must be finalized.
The Trust Board approves projects with conditional or final certification.
Borrowers submit final written comments to Draft #2 of the Loan, Escrow and Continuing Disclosure Agreements, including the borrower’s disclosure for Preliminary Offering Statement, to the Trust and the Trust’s Bond Counsel, General Counsel and Financial Advisor.
Borrowers and the DEP agree on final Trust and Fund Loan amounts and Loan Agreement Draw Schedules.
Trust/Borrower escrow closings are held at the Trust Bond Counsel’s offices.
Borrowers are not allowed to accept bids during a specified black-out period (August 15).
   
September
Conditional Project Certifications are approved at the Trust Board’s meeting.
   
October
The Trust disseminates Preliminary Offering Statements
The Trust publishes the Summary of Notice of Sale
The Trust holds Bond Sale/Purchase of Investments.
Borrowers receive Trust Loan amounts and Trust and Fund Loan repayment schedules from the Trust Financial Advisor.
Confirmatory resolutions are adopted by borrowers finalizing Trust Loan amounts and Trust and Fund Loan repayment schedules.
The Trust prints Offering Statements and distributes to successful bidders.
   
November
Borrower closings are held.
Financing pre-closing and closing held at the Trust Bond Counsel’s Offices.
End of the bid black-out period.

 

New Jersey Environmental Infrastructure Trust
3131 Princeton Pike, Bldg. 6, Suite 201
Lawrenceville, NJ 08648

Copyright © 2010 NJEIT

» Driving Directions
» Phone: (609) 219-8600 » Fax: (609) 219-8620

» Site Index

Last Update: July 7, 2010